Location: 96 miles away from Da Ya Wan
Water Depth: 100m
Working Period: Late in July 2011
After 90days continuous fighting, DE KUN had successfully assisted COOEC’s LAN JIANG pipe-lay vessel in the HZ 19-2 pipe-laying project which pipeline was 36km, and the project had completed 10 days ahead of the schedule. The working condition is complicated, some drilling platforms were near the work site, the distribution of the pipeline and cables were complex. During that time it was typhoon season, the sea condition is not great for the work, the wind speed always reached to level 6 and the wave could rise to 3 meters high.